Google has halted the construction of its artificial intelligence data center in Belgium. This decision was made after local authorities announced that the company was operating without the required planning permits.
Work Stoppage at Data Center Site
A spokesperson for Google, Michelle Salats, stated: "We have halted work based on the order of local authorities and are awaiting further guidance." She added: "We have been operating in Belgium for over 15 years and are committed to complying with local laws." This statement was issued after Walloon authorities gave 300 workers a verbal order to stop work at the site in Ecofol.
Read more: UK Education Minister Warns of Rising Cyber Attacks
Dispute Over Permits
Robert Stouckis, an official from the Walloon Ministry of Planning and Urban Development, said: "A building covering 30,000 square meters was nearly completed, while the permit had been rejected by the minister." This suspension followed an immediate legal action by the environmental group Greenpeace due to the continued construction by Google while the revised permit had been invalidated.
Google initially received a permit in 2024 to build three data centers in Belgium using an air cooling system. However, after receiving the permit, the company requested a modification, reducing the number of data centers from three to two and switching to a water-based cooling system fed by the Sambre River.
The revised permit was issued in April 2026, but was invalidated in August due to a third-party objection. Google continued work at the site while appealing this decision. The company claims to have several other permits for the development of the data center that remain valid. The work carried out since August has primarily been for maintenance and securing the site during the appeal process.
The ongoing dispute comes as opposition to the construction of data centers, which power the global artificial intelligence boom, is increasing, and the extensive energy and water needs of these centers have become a political flashpoint for communities and local governments.